Schedules
appear on the internet which do not seem to have a logical sequence in the
firing schedule. Some have multiple
soaks at intervals up to 540°C. Others
have kind of dance toward the top temperature – slow, quick, slow. Some initially cool at a given rate and then
slow to about half that initial rate.
Multiple soaks
These
schedules have been referred to as catch-up schedules. They tend to look something like this:
200°C to 150°C for 20 minutes
250°C to 300°C for 20 minutes
300°C to 590°C for 20 minutes
50°C
to 677°C for 30 minutes
330°C to 804°C for 10 minutes
AFAP
to 482°C for 60 minutes
60°C
to 370°C for 0 minutes
Off
The
justification for the first two soaks is given as allowing the glass to catch
up to the air temperature. It would be
much safer for the glass to have a moderate steady advance in temperature
rather than risking the heat shocking of the glass. You could achieve the same work in the same
amount of time by altering the rate of advance to a single one of 198°C to
590°C. This achieves the same
temperature in the same amount of time, but has less risk of heat shock, as
there is a steady input of heat.
Secondly, if the glass can survive the initial rate of heat up without breaking, there is no need to soak at an arbitrary temperature. The first relevant point where a change in temperature makes sense is above the softening point, which for most fusing glasses is about 540 °C. The equivalent softening point for float glass is about 700°C
Secondly, if the glass can survive the initial rate of heat up without breaking, there is no need to soak at an arbitrary temperature. The first relevant point where a change in temperature makes sense is above the softening point, which for most fusing glasses is about 540
Slow, quick, slow
This kind of schedule alters rates up
and down with little justification as far as I can see. This is an example:
139°C to 560°C for 30 minutes
222°C to 621°C for 30 minutes
139°C to 786°C for 15 minutes
9999 to 515°C for
120 minutes
60°C to 427°C for
10 minutes
115°C to 350°C for 10 minutes
The question for me is why the slow
down to top temperature. There is a lot of heat work being put into the glass,
so that the higher top temperature may not be required. The slower rate from 621°C does allow a form
of a bubble squeeze to occur, but is not the traditional one. A 139°C rate from 621°C to 677°C with a soak would be faster than usual,
but may be acceptable. I would prefer 50°C
per hour with a 30-minute soak at the end.
Then advancing at 300°C per hour to top temperature. The anneal soak and cool of this schedule are
acceptable, even though different than I would do it.
Erratic Slumping Schedule
The fusing schedule above was
followed by this slumping schedule:
83°C to 148°C 15 minutes
167°C to 590°C 10 minutes
83°C to 720°C 10 minutes
222°C to 410°C 120 minutes
83°C to 427°C 10 minutes
This schedule seems to have
a catch-up phase in that it goes at half speed for the first 148°C and then
doubles the speed to 590°C (a little above the brittle phase of the
glass). It then slows the rate and
continues that to a very high slump temperature. It is, of course, necessary to have a slower
rate of advance in the slumping than the fusing, as the piece is now thicker. Slowing
the rate of advance as much as in this should be able to achieve the slump at
around 620°C (100°C) less than the target temperature used by the
schedule.
Once the top temperature
soak is finished, a very slow cool to the annealing soak is used in this
schedule. This is not ideal as it
invites devitrification to form. The
kiln and its contents should be allowed to cool as quickly as possible to the
temperature equalisation soak at the annealing point.
The schedule then uses an
annealing soak temperature 100°C below that used for the fusing. This does not
make sense. The annealing soak should be at the same temperature for both
firings. The length of the soak is not
in question, but the early turn off the kiln at 427°C is questionable. The
anneal cool of the fused piece extended down to 350°C. The anneal cool on slumping should be almost
the same as the fuse. Almost all anneal
cools extend to 370°C at least.
Anneal Cools
Some
anneal cools have erratic rather than progressive cooling. In this example the early part of the
schedule is eliminated:
……………..
AFAP to 482°C
120 minutes
110°C to 427°C
0 minutes
55°C to 370°C
0 minutes
200°C to 100°C
0 minutes
off
Here
the schedule is faster in the most critical part of the anneal cool than in the
next, cooler part. This will not provide
as good an anneal as if the first two segments after the equalisation soak were
reversed. Start slowly in the anneal
cool and then you can speed up (approximately twice the previous segment rate)
on each of the following segments.
Rationale
This
critique of the schedules above is not to batter anyone. It is to make clear that there needs to be a
conscious rationale for each of the segments in relation to the others. If you take a schedule from a source, it is a
good idea to see if there is a reason for each segment and how it relates to
the next.
·
The scheduling must take account of the
nature of the glass. Glass is a poor
conductor of heat and needs steady moderate input of heat.
·
Glass is brittle until approximately 55°C
above the annealing temperature when you can accelerate the rate of advance.
·
Time is required to allow air out from
between the layers of glass. This usually done in the range of 620°C to 675°C
and is known as the bubble squeeze.
·
You need to go relatively quickly through the
devitrification range of temperatures – approximately 700°C to 760°C - both up and down.
·
Glass needs a temperature equalisation soak
at the annealing point (or nearby) related to its thickness.
·
The rate of cooling needs to be
progressive. The first 55°C below the
annealing soak is the most important.
·
Cooling rates must be related to thickness.
·
The second cooling rate can be up to double
the initial one.
·
The final cooling rate can be double the
previous one.
·
The rate of firing will affect the required
top temperature.
No comments:
Post a Comment